DATE: 9/19/05

                         

                                                                                    

                                                                                                                                                                                                                             

 

 SUBJECT: Bi-weekly report for Ray Hartstein Campus Art, Science and Technology Pavilion

 

This month action:

 

·        The temporary smoke doors on the second floor of the North wing have been installed.

·        The wood doors for the multipurpose room have been installed.

·        The video and sound system for the multipurpose room has been installed.

·        The existing East wing building has been fully abated.

·        The existing East wing building 1st and 2nd floor has been cleaned out.

·        The water and power have been shutoff in the old high school building.

·        The building will start being dismantle on Monday 9/19/05 and will be completed by Friday 9/30/05.