Construction

An image of Oakton College's Des Plaines campus office rennovations.

Liberal Arts, Academic Affairs and Institutional Research Office Renovations (Des Plaines Floor 2)

Stakeholder(s):

Office of Academic Affairs, Office of Liberal Arts, Office of Institutional Research

Percent Complete:

45%

Project Start:

04/08/2024

Project Completion:

01/17/2025

Phase 1 has been completed. The Liberal Arts Department has moved into Suite 2180, and the Institutional Research has moved into Suite 2100. 

Academic Affairs has moved temporarily into Suite 1420 while construction takes place on Floor 2.

Phase 2 of construction is tentatively scheduled to begin in the existing Liberal Arts and Academic Affairs suites on Aug. 5.

An image of the Skokie  Library Learning Commons Construction update.

Skokie Library Learning Commons

Stakeholder(s):

ADRC, Learning Center, Library, Testing Center, TRIO

Percent Complete:

95%

Project Start:

12/18/2023

Project Completion:

07/31/2024

The contractor is working to complete the punch list. Furniture is scheduled for installation the week of July 15. Department moves are tentatively planned for July 29 - Aug. 9.

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

10%

Project Start:

TBD

Project Completion:

TBD

Kluber Architects is working on construction documents for phase 1, which entails repairs and replacement to exterior doors across both campuses. Construction dates will be established upon completion of construction documents and bidding process.

An image of updated Signage at Oakton College.

Signage Update

Percent Complete:

99%

Project Start:

11/22/2021

Project Completion:

07/26/2024

All interior signs have been installed and corrections to signage are complete. All exterior signage is installed except for new signage at door 5 at Des Plaines, which will be installed in July 2024.

An image of the master construction plan at Oakton College.

Landscape Master Plan Project

Percent Complete:

65%

Project Start:

10/23/2023

Project Completion:

07/26/2024

Work is progressing across both campuses. Door 5 at Skokie is expected to remain open throughout construction. 

Work at door 5 at Des Plaines has begun and is scheduled to be completed by July 26. Work at door 5 will include demolition and replacement of concrete, construction of new benches and installation of new landscaping.

Concrete work in front of the Lee Building will resume on July 22 and be completed by July 26.

An image of the Oakton College Leaf on a grey background.

Baseball Field Renovation

Stakeholder(s):

Athletics Department

Percent Complete:

50%

Project Start:

Spring 2023

Project Completion:

Fall 2024

Field demolition and sub-grading is completed. Surveying crews are verifying surface grade elevations and irrigation system installation has begun. The parking lot update is scheduled for spring 2025. 

Appears to be an image of Oakly waving outside at Oakton College's Des Plaines campus.
Student Affairs
The Student Affairs Department is moving temporarily to Room 2817 at the beginning of August. The new space is currently being designed, with the department moving to Floor 1 in the summer or fall of 2025.
An image of Oakton College's Ten Hoeve Construction.

Small Business Development Center and Educational Foundation (at Des Plaines TenHoeve Center)

Stakeholder(s):

Educational Foundation, Small Business Development Center (SBDC)

Percent Complete:

100%

Project Start:

12/1/2023

Project Completion:

06/28/2024

Department moves have been completed.